Install and commission commercial refrigeration and air conditioning
Level | 3 |
Credits | 15 |
Purpose This unit standard is for people who work, or intend to work, in the refrigeration and air conditioning sector of the engineering industry, and is intended for use in the training of installers and technicians of refrigeration and air conditioning equipment.
People credited with this unit standard are able to: demonstrate knowledge of pre-installation activities for refrigeration and air conditioning systems; install the components of refrigeration and air conditioning systems; perform pre-start commissioning procedures; perform start-up commissioning procedures; and provide information to operators and complete required documentation.
Subfield | Mechanical Engineering | |
Domain | Refrigeration and Air Conditioning | |
Status | Registered | |
Status date | 20 June 2006 | |
Date version published | 20 June 2006 | |
Planned review date | 31 December 2011 | |
Entry information | Open. | |
Replacement information | This unit standard replaced unit standard 3834 and unit standard 3839. | |
Accreditation | Evaluation of documentation and visit by NZQA. | |
Standard setting body (SSB) | Competenz | |
Accreditation and Moderation Action Plan (AMAP) reference | 0013 | |
This AMAP can be accessed at http://www.nzqa.govt.nz/framework/search/index.do.
Special notes
1 References
Building Act 2004;
Electricity Act 1992;
Electricity Amendment Act 1997;
Hazardous Substances and New Organisms Act 1996;
Health and Safety in Employment Act 1992;
Ozone Layer Protection Act 1996;
Electricity Regulations 1997;
AS/NZS 1677:1998, Refrigerating systems – Refrigerant classification;
AS/NZS 3000:2000, Electrical installations;
Code of Practice for the reduction of emissions of fluorocarbon refrigerants in refrigeration and air conditioning applications. Institute of Refrigeration, Heating and Air Conditioning Engineers of New Zealand (IRHACE New Zealand), 2001. Available from IRHACE, 28 E Lambie Drive, Manukau City.
2 Definitions
Commercial refrigeration and air conditioning systems refers to items such as: refrigeration equipment as found in retail food outlets, truck and shipping-container refrigeration, horticultural cool room refrigeration, controlled atmosphere fruit stores;
and air conditioning equipment as found in commercial buildings.
Organisational procedures refer to documents that include: organisational rules, codes, and practices; equipment operating instructions; production specifications; documented quality management systems; and health and safety requirements.
Elements and performance criteria
Element 1
Demonstrate knowledge of pre-installation activities for refrigeration and air conditioning systems.
Performance criteria
1.1 Installation drawings, schedule of materials, and instructions are described in terms of checks that should be made against site conditions.
1.2 Two examples are given of modifications that may be required to suit site conditions.
1.3 Procedures for assembling materials and verifying them against a schedule of materials are described.
1.4 Procedures for verifying ancillary service connections and reporting any discrepancies are described.
Range may include but is not limited to – water, electricity, plumbing.
1.5 Two examples are given of situations where permits and/or consents are required for installations.
Element 2
Install the components of refrigeration and air conditioning systems.
Performance criteria
2.1 Major components are positioned and secured in accordance with drawings, designs, specifications, and instructions.
Range refrigeration components include but are not limited to – compressor, condenser, evaporator, metering device;
air conditioning components include but are not limited to – compressor, outdoor fan coil, metering device, indoor fan coil.
2.2 Ancillary components and installation materials are installed in accordance with drawings, designs, specifications, installation considerations, and instructions.
Range ancillary components may include but are not limited to – valves, controls, filters, driers;
installation materials may include but are not limited to – supports and bracketing to secure pipework, piping, tubing, capping, thermal insulation;
installation considerations may include but are not limited to – nitrogen purging, internal cleanliness.
2.3 The work of associated tradespeople is identified and reported in accordance with organisational procedures.
Element 3
Perform pre-start commissioning procedures.
Performance criteria
3.1 Safety devices are tested and calibrated and systems are verified as safe to be exposed to operating pressures.
3.2 Controls are tested and set to meet specified performance and safety requirements.
Range controls equipment may include but is not limited to – programmable logic control (PLC), electronic, electromechanical, pneumatic.
3.3 Electrical systems are checked, and compliance with performance and safety requirements is verified.
Range checks include but are not limited to – earth continuity, insulation resistance, polarity, voltage.
3.4 Visual and tactile tests are performed to ensure the mechanical integrity of all electrical terminations and connections.
3.5 Motor ratings are verified against fuse ratings and overload settings.
3.6 Motor and pump rotation directions are verified.
3.7 Fluid flows are tested and balanced as required.
3.8 Actions are taken as required to clear foreign solid matter from pipe-work and/or associated components.
3.9 System and component integrity is confirmed by the use of appropriate leak detection methods and equipment.
3.10 Compressor is checked and, if required, charged with appropriate lubricant.
3.11 System is evacuated to pull down to 500 microns or less to ensure that moisture, oxygen, and non-condensables are removed.
Range evacuation tools include but are not limited to – Schraeder core removal tool, vacuum analyser, vacuum pump, short large-bore vacuum hose, solenoid valve, isolating valves.
3.12 Where triple evacuation is required, vacuums are broken with dry nitrogen.
3.13 Vacuums are broken with appropriate refrigerant after final evacuation.
Element 4
Perform start-up commissioning procedures.
Performance criteria
4.1 System is checked and charged using appropriate method and refrigerant in accordance with system specifications.
Range method may include but is not limited to – suction super-heat set and sub-cooling checked after system is running and stabilised, compressor current measured and control settings verified for operational performance, lubricant and/or refrigerant levels and flows adjusted as necessary for required performance.
4.2 Lubricant and/or refrigerant identification labels are affixed to appropriate parts of the system in accordance with legislative requirements.
4.3 System performance data is recorded as required by operational specifications and instructions.
Range temperatures, pressures, super-heat, sub-cooling, current draw, fluid flows, humidity, noise, vibration.
Element 5
Provide information to operators and complete required documentation.
Performance criteria
5.1 Operators are familiarised with manuals and operating instructions.
5.2 Operators are instructed to operate refrigeration and air conditioning systems within design parameters, and in accordance with operational and worksite procedures.
5.3 Documentation is produced outlining labour and materials used, and any details required for a warranty in accordance with organisational procedures.
Please note
Providers must be accredited by the Qualifications Authority, or an inter-institutional body with delegated authority for quality assurance, before they can report credits from assessment against unit standards or deliver courses of study leading to that assessment.
Industry Training Organisations must be accredited by the Qualifications Authority before they can register credits from assessment against unit standards.
Accredited providers and Industry Training Organisations assessing against unit standards must engage with the moderation system that applies to those standards.
Accreditation requirements and an outline of the moderation system that applies to this standard are outlined in the Accreditation and Moderation Action Plan (AMAP). The AMAP also includes useful information about special requirements for organisations wishing to develop education and training programmes, such as minimum qualifications for tutors and assessors, and special resource requirements.
Comments on this unit standard
Please contact Competenz qualifications@competenz.org.nz if you wish to suggest changes to the content of this unit standard.
DIPLOMA TRANSPORT PROJECT
Prepare a unit quote and approximate running cost for the first twelve months of use including service costing.
The following parameters can be assumed to be given for all examples.
Summer average daytime ambient temp 28 c
Summer average night ambient temp 15 c
Winter average daytime ambient temp 12 c
Winter average night ambient temp 5 c
The first vehicle will be a semi-trailer, multi-temp unit carrying 7tons of ice-cream at -25c, at a maximum weight of 900kg/pallet, also 12tons of butter at 5c,at the same maximum pallet weight.
The second vehicle will be a 7.5ton rigid single temp vehicle to carry up to 4tons of frozen products at a minimum of -20c, at a maximum pallet weight of 800kg/pallet.
It is to be assumed the trailer is on trunking duty between Auckland and wellington ,leaving at 5am taking 12hours, returning with dry-freight the fridge unit switched off. Three runs/week to be carried out following this timetable.
The rigid however is to carry-out multi-drop duties in Auckland, this will cover a five day working week, twenty (20) drops /day of 10 mins duration. each day comprising 10hrs, also starting at 5am each day.
The units are to be built to N.Z. normal build standards which you are to research, the most fuel efficient design is to be used. Food standard guidelines are to be strictly adhered to in all cases.
The units to be used have been specified by the customer to be CARRIER, the vehicle bodies are at your discretion, you are to follow manufacturers recommended service intervals, service costs are as follows:-
First service 400hrs F.O.C. (all units )
1000hr service $ 450 rigid units
1000hr service $ 700 trailer units
5000hr service $ 1200 rigid units
5000hr service $1500 trailer units
You are only to use the guidelines and selection tables supplied to size the units , running times are to be calculated by thermal loss through body , a 20% air change per door opening in the case of multi-drop usage and all products are at correct temperature on loading. Trunking usage you can assume no door openings during transit.
Daytime average temperatures are to apply 9am to 9pm, all operations outside these times you are to apply night temperatures.
Fuel usages are as follows:-
Truck unit low speed 3ltrs/hr
Truck unit high speed 4.5ltrs/hr
Trailer unit low speed 4ltrs/hr
Trailer unit high speed 7ltrs/hr
All units will start in high speed, will run on high speed until within 3 degrees of set-point, then run on low speed down to set-point and stop. Units will not restart until 3 degrees above set-point and will always restart in high-speed.
The effects of any surface cooling due to windage while travelling are to be ignored, as are any losses due to vehicle body damage or moisture ingress at seams. These are to be considered as new vehicles.